FS#955 — FS#4976 — RBX2 : Prevetive maintenances of UPS

Attached to Project— Datacenters
Maintenance
Roubaix 2
CLOSED
100%
Preventive maintenances on the UPS pool of Roubaix 2.
These maintenances concern 2 essential subjects:

1- Verify and fix there where it is necessary to mount the batteries of the different UPS. In fact, following the different problems which we have encountered recently (http://travaux.ovh.net/?do=details&id=4871 among other things), the experts has pointed the batteries montage. The set of the pool of this brand will be verified and fixed there where it is necessary.

2- Improvement of draughtproofing of cable entries. The cables bring in and bring out in big quantities the UPS yet are not sufficiently draught proofed, which limits the quality of air filtration in the UPS entries. The modification which will be made is going to be be a considerable amount of time saving in maintenance and in crash risk to come.




We will start with UPS 7 (room 26).
The UPS will be by-passed during the modification of cable entries.
For the batteries, the verification will be made on the spot (isolation branch batteries by branch batteries).
Date:  Thursday, 30 December 2010, 15:19PM
Reason for closing:  Done
Additional comments about closing:  The modifications and test were done. It happened as expected.

The whole parc is operational.
Comment by OVH - Tuesday, 28 December 2010, 12:05PM

The maintenance on the cable entries was done on UPS 7.
We do it now on UPS 8.


Comment by OVH - Tuesday, 28 December 2010, 12:05PM

UPS 8 was finished. UPS 6 now.


Comment by OVH - Tuesday, 28 December 2010, 12:06PM

UPS 6 finished
UPS 5 ongoing


Comment by OVH - Tuesday, 28 December 2010, 17:26PM

Maintenance on the entrances cables are completed.

We perform maintenances on batteries, starting now
with UPS 7 (room 26)


Comment by OVH - Wednesday, 29 December 2010, 14:24PM

We will continue this morning the maintenance on the cable entries
(that we are doing this morning)

Working on UPS is in progress.


Comment by OVH - Wednesday, 29 December 2010, 14:25PM

Working on UPS 4 is in progress.


Comment by OVH - Wednesday, 29 December 2010, 14:26PM

UPS 3 in in progress.


Comment by OVH - Wednesday, 29 December 2010, 14:27PM

We will switch to Roubaix 3.
UPS 1 RBX3 is in progress.


Comment by OVH - Wednesday, 29 December 2010, 14:31PM

UPS 2 is done now.
UPS 4 RBX3 in progress.


Comment by OVH - Thursday, 30 December 2010, 15:16PM

All the maintenances were done.

We are going to finish with an individual battery test of which
inverter. We are going to simulate a tesion absence in entry and
discharge the batteries during 1 minute to validate
the good functionning of the whole installation.

These last tests will be done between 11h30 and 13h
this thursday 12/30/2010 on the whole parc of this
mark (UPS 3 a 8 RBX2, UPS 1 2 et 4 RBX3).