FS#9144 — FS#13004 — bru-1-6k
Attached to Project— Network
Modernization | |
Backbone EU | |
CLOSED | |
![]() |
Today is a great day for our network, we are producing the first 100G equipment ready on the Brussels POP.
The operation is scheduled from 23:00 CEST. We will redirect traffic to BNIX while it takes place..
Date: Thursday, 09 April 2015, 10:22AMThe operation is scheduled from 23:00 CEST. We will redirect traffic to BNIX while it takes place..
Reason for closing: Done
We've isolated the router.
We will migrate the links to the Arista.
All the fibres are migrated. The Arista is live.
We will monitor to make sure that there's no CRC and that the new optic cables are OK.
All the indicators are green. We will reroute the traffic!
The Brussels POP is now 100G ready:
bru-1-a72#sh inter status | i 100G
Et49/1 I:rbx-g1-a75:OVH: notconnect in Po1161 full 100G 100GBASE-SR1
Et50/1 I:rbx-g2-a75:OVH: notconnect in Po1162 full 100G 100GBASE-SR1
Next step: we will turn on the 100G port! :)