FS#8851 — FS#12717 — VPS Low Latency - Newark / Frankfurt
Attached to Project— VPS
Maintenance | |
Infrastructure | |
CLOSED | |
![]() |
VPS in the Newark PoP will be migrated on Tuesday 3 March at 10:00 (GMT+1).
VPS in the Frankfurt PoP will be migrated on the same day at 23:00 (GMT+1).
Newark VPSs will be migrated to our BHS infrastructure and those in Frankfurt will be migrated to SBG.
There will be service downtime during the time it takes to synchronise the VPS and switch over the routing.
Date: Wednesday, 04 March 2015, 09:25AMVPS in the Frankfurt PoP will be migrated on the same day at 23:00 (GMT+1).
Newark VPSs will be migrated to our BHS infrastructure and those in Frankfurt will be migrated to SBG.
There will be service downtime during the time it takes to synchronise the VPS and switch over the routing.
Reason for closing: Done
Currently migrating the VPSs
All the Newark VPSs have been migrated
Starting to tmigrate the VPS in Frankfurt
Migration of VPS in FRA to SBG complete