FS#8319 — FS#12190 — BHS : High Voltage line transfer

Attached to Project— Datacenters
Maintenance
Beauharnois
CLOSED
100%
In order to free the line 1438 (120kV), we will perform a line transfer this Thursday, December 11th, 2014 to take power from the line 1436 (120kV).

No cut-offs are expected.
Date:  Thursday, 18 December 2014, 03:34AM
Reason for closing:  Done