FS#783 — FS#4822 — setting up of asr-g1-a9 in the backbone
Attached to Project— Network
Maintenance | |
Whole Network | |
CLOSED | |
![]() |
We will add the new router asr-g1-a9 in the backbone.
Him and his brother have to take in charge
the routing between the inside of our data centres at Roubaix
and the outside of our data centres, that is to say the routes
towards Paris, London, Bruxelles, Amsterdam, and Frankfurt.
Date: Friday, 12 November 2010, 11:20AMHim and his brother have to take in charge
the routing between the inside of our data centres at Roubaix
and the outside of our data centres, that is to say the routes
towards Paris, London, Bruxelles, Amsterdam, and Frankfurt.
Reason for closing: Done
It is done.