FS#7132 — FS#11021 — vKS Migration
Attached to Project— VPS
Modernization | |
Infrastructure | |
CLOSED | |
![]() |
We will intervene in the night from Tuesday 24th to Wednesday, June 25th, 2014 from 11:00 pm to move virtual servers of VKS range. This will be done in accordance with the mail that was previously sent to customers. Service cut-off is expected when we will switch them.
Date: Thursday, 26 June 2014, 10:19AMReason for closing: Done
We started the intervention.
A dozen of vhost was imported, everything goes as planned, we are accelerating the operation.
The vast majority of VKS have been imported. A few things remain to be manually addressed. We will take care of these.
The VKS upgrade to VPS2014 has been dealt with overall. We are still dealing with a vhost which will have an impact on a few VPS.