FS#6727 — FS#10620 — BHS : electrical switching
Attached to Project— Datacenters
Maintenance | |
Beauharnois | |
CLOSED | |
![]() |
Several tests of electric switching will be done this Monday, April 14th and Tuesday, April 15th in order to establish an automated of power management.
No failure is expected, generators and UPS will take over during the various tests.
Date: Wednesday, 16 April 2014, 15:54PMNo failure is expected, generators and UPS will take over during the various tests.
Reason for closing: Done