We're going to set up a new VoIP infrastructure, which will be named C.
This infrastructure will complement the existing cluster (Infrastructures A and B).
Installation is planned for this week, and deployment within 15 days.
Update(s):
Date: 2014-06-16 06:54:48 UTC No more active lines on the old infrastructure.
Date: 2014-06-06 10:47:04 UTC Less than 200 active lines remain on the old infrastructure.
Date: 2014-06-05 15:04:24 UTC Less than 500 active lines remain on the old infrastructure.
Date: 2014-05-06 12:43:04 UTC The lines migrations onto the new infrastructures are in the final phases.
Less than 10,000 lines now remain on the old infrastructure (c4).
Date: 2014-04-04 00:58:52 UTC Updates have now resumed normal activity.
Date: 2014-04-04 00:58:36 UTC Synchronization is now complete. Slowdowns are absorbed at 75%.
Date: 2014-04-04 00:46:47 UTC We started the data synchronization.
Date: 2014-04-04 00:46:29 UTC A synchronization of the infrastructure database is programmed for 04/03/2014 at 03:00 pm for 30 minutes. Part of updates via manager will be slow during this period.
Date: 2014-03-31 08:31:35 UTC We're migrating the first internal lines.
Date: 2014-03-27 08:54:22 UTC We're starting the final synchronisation of the databases and the emergency devices.
Date: 2014-03-12 04:49:14 UTC Installation completed.
Tests started.