FS#65 — FS#4179 —power cut RBX1 + RBX2 + RBX3
Attached to Project— Datacenters
Incident | |
Existing | |
CLOSED | |
![]() |
We have just had a power cut in each of our data centers in Roubaix.
Each data center is moved to a generator then the electric current was restored quickly.
There was no consequence to this EDF power cut.
Date: Thursday, 13 May 2010, 18:31PMEach data center is moved to a generator then the electric current was restored quickly.
There was no consequence to this EDF power cut.
Reason for closing: Done