FS#6288 — FS#10189 — Switching to spare supply
Attached to Project— Datacenters
Maintenance | |
Roubaix 2 | |
CLOSED | |
![]() |
ERDF let us know this morning that the Roubaix 2 supply must be switched to the spare cable.
Work in progress now.
Date: Tuesday, 11 February 2014, 21:21PMWork in progress now.
Reason for closing: Done
We have switched to the spare one (no downtime).
This is preventive maintenance of HTA circuit breakers in the substation that feeds the NORMAL cable.
The normal cable should be back this afternoon.
The back to normal is done on Monday at the afternoon.