FS#6153 — FS#10059 — Cellules HT

Attached to Project— Datacenters
Maintenance
Strasbourg 1
CLOSED
100%
During the last generators test, we noticed a problem on an inverter cell HTA.
According to the manufacturer who was on site, the problem would be related to the control relay of this cell that does not change their status. Given the tests that were performed and the results obtained, we will proceed to replace all the electronics of the cell + automaton.

The operation is planned for Monday, 27/01/2014
Date:  Friday, 31 January 2014, 01:50AM
Reason for closing:  Done
Comment by OVH - Friday, 31 January 2014, 01:49AM

The intervention can not be 100% done today as a consignment of the cell is necessary for the last elements.
We will re-supply the website with another circuit to set to earth these cells.
The rest of the operation will be held on Wednesday.


Comment by OVH - Friday, 31 January 2014, 01:50AM

The manufacturer teams have succeeded thereafter several times to fix the issue.
The whole installation has found 100% of its functionalities.