FS#5997 — FS#9905 — BHS : Test Generators
Attached to Project— Datacenters
Modernization | |
Beauharnois | |
CLOSED | |
![]() |
We will proceed to a load test of the new generator supply one of the routing paths.
The test will be done on Wednesday 18/12/2013 at 10:00 EST.
No cutoff is expected.
Date: Friday, 20 December 2013, 07:22AMThe test will be done on Wednesday 18/12/2013 at 10:00 EST.
No cutoff is expected.
Reason for closing: Done
The test had to be postponed for tomorrow morning: 19/12/2013 .