FS#5952 — FS#9862 — HT portection adjustment

Attached to Project— Datacenters
Maintenance
Gravelines
CLOSED
100%
We carrying out an adjustment of the main HTA circuit breaker (again because ERDF did it incorrectly last time).
We will move onto the generator during the adjustment.

Date:  Thursday, 12 December 2013, 11:58AM
Reason for closing:  Done