FS#5878 — FS#9792 — BHS : Adding a new generator
Attached to Project— Datacenters
Modernization | |
Beauharnois | |
CLOSED | |
![]() |
To add a generator on one of routing channels as well as the alpha room (rack 80A), we will perform a series of switching Wednesday, December 4th, 2013 at 10:00 am EST.
No cut-off expected since UPS will take over during the maintenance.
Date: Thursday, 05 December 2013, 09:06AMNo cut-off expected since UPS will take over during the maintenance.
Reason for closing: Done
Additional comments about closing: The switchovers are finished.
We're starting the switchovers.