Since 10:45pm, we have an increase in voltage supplied by EDF causing minor alarms on a cluster of UPS behind the transformer n°6.
Nothing serious. They receive 420V instead of 410V.
We will perform a re-adjustment of the transformer tomorrow morning.
Date: Friday, 12 April 2013, 12:32PMNothing serious. They receive 420V instead of 410V.
We will perform a re-adjustment of the transformer tomorrow morning.
Reason for closing: Done
The voltage level is normal since midnight.
We will proceed this morning to decrease setting TR6.
Settings are done.
End of work.