Currently these 2 routers have no longer 10G port available .
Each router has eight cards, each consisting of 8 ports 10G.
To add network capacity, we have to change a 8x10G card by one with 24x10G.
To do this we should change the Supervisors of each router. (via the RSP-2 RSP-440).
We will start maintenance at 00:00. (CET)
Update(s):
Date: 2013-03-07 04:48:57 UTC Done
Date: 2013-03-07 04:48:50 UTC Done,
we will restore traffic.
Date: 2013-03-07 04:48:29 UTC We started to insert the new 24x10G card .
Date: 2013-03-07 04:47:54 UTC The router is up.
We are updating linecards.
Date: 2013-03-07 00:25:48 UTC The router is isolated. We'll turn it off in order to change Supervisor.
Date: 2013-03-07 00:24:31 UTC We are moving to a th2-g1-a9 now.
We are isolating the router from the network.
Date: 2013-03-07 00:24:04 UTC Done.
We are restoring traffic.
Date: 2013-03-07 00:23:46 UTC We are updating the linecards.
Date: 2013-03-07 00:23:28 UTC The new RSP 440 are starting.
Date: 2013-03-07 00:23:08 UTC The router is isolated.
We turned off the router in order to change cards.
Date: 2013-03-07 00:22:29 UTC We started with gsw-g1-a9.