Get webhook notifications whenever Network & Infrastructure creates an incident, updates an incident, resolves an incident or changes a component status.
Date: 2013-01-08 18:55:42 UTC We turned the UPS on and switched the room to the EDF network then moved to UPS mode.
Date: 2013-01-08 00:35:19 UTC The room 9 has been switched temporarily to a generator (on hot).
The inverter 11 has been replaced and cabled this afternoon / night.
The manufacturer of the new inverter will be there at 08:00am, tomorrow morning to set the service.
We are keeping the room 9 tonight on the generator ( loaded to about 25% )
Date: 2013-01-07 08:31:49 UTC The work hasn't been performed Friday, we had to find another plan.
We start manipulations this morning.
Date: 2013-01-03 18:40:02 UTC There is a transformer in an uninterruptible power supply. There was an electric arcing in the transformer and it is now in default.
Replacement of the transformer being particularly complicated and time consuming, we have decided to replace the entire UPS by one that we have in stock.
The operation will begin tomorrow, Friday morning at 5:00 am and will probably end on Saturday 12pm.