FS#3098 — FS#7051 — Router room generator
Attached to Project— Datacenters
Modernization | |
Beauharnois | |
CLOSED | |
![]() |
To secure path B of the router room,
At around 10:30 am we will add a generator to path B (Hydro Quebec).
No interruption is to be expected since path A is not impacted and it on UPS.
Date: Friday, 02 November 2012, 16:53PMAt around 10:30 am we will add a generator to path B (Hydro Quebec).
No interruption is to be expected since path A is not impacted and it on UPS.
Reason for closing: Done
The switch transfer is cabled and operational. The group was restarted.
The tests are concluding.
We are going to make the same intervention for the 2nd router room.