A technician is working to audit the optical link.
Update(s):
Date: 2012-06-06 20:20:32 UTC The fibers are welded.
The NRA are operational.
Following to the new weld we move from -18.4 to -19db
All websites are UP.
Date: 2012-06-06 20:16:04 UTC Welds are being processed.
Date: 2012-06-06 20:15:06 UTC SFR has finally found an interruption on the fiber.
Technicians are on site since 5pm.
The cable was partially defective.
It was cut a 5pm50 by the teams on site.
The cable is currently being prepared for welding.
The beginning of welds is expedted between 7:30pm and 8pm.
It is a 144 FO to weld.
Date: 2012-06-06 15:02:32 UTC The optical link is operational in the sense JOL13 -> FER13. whereas, the light is turned off in the direction FER13 -> JOL13. We expect an FT audit in the dispatchers rooms.
Date: 2012-06-06 13:47:49 UTC The interruption is not yet localized. We seek the origin of the interruption on the fiber.
Date: 2012-06-06 13:22:07 UTC The technician is on the first site.
We check the links.
Date: 2012-06-06 13:21:16 UTC The technician will be on the site at 14h.