FS#2651 — FS#6612 — Cooling maintenance

Attached to Project— Datacenters
Maintenance
Roubaix 1
CLOSED
100%
We will perform preventive maintenance on the cooling systems in Roubaix romms 3 4 5 6 and 7 (racks 03xxx 04xxx 05xxx 06xxx 07xxx).
Only 33% of the installation will be turned off for a deep maintenance. Cooling will be provided by the other redundant systems of these rooms.

The operation will take place tomorrow Thursday morning between 8:30 and 10am.
Date:  Monday, 23 April 2012, 17:06PM
Reason for closing:  Done