We are going to start several updates for the configuration of our switches.
Each switch will be rebooted which will cause a network outage between 2 and 4 minutes for servers connected to it.
Work will be done in the morning between 6am and 8am from monday, 09.01.2012.
We will start this monday with the networks 213.251.*.* and 87.98.*.*
Update(s):
Date: 2012-02-14 07:49:04 UTC Roubaix 3 188 165 networks. *. * were started last night.
Tonight we had a network interruption of several minutes on four switches:
Date: 2012-02-07 08:41:55 UTC We have terminated Roubaix 2.
We start this night the datacenter of RBX3 on networks 188.165.*.*
Date: 2012-02-01 20:01:22 UTC The workings on the switches of the networks 94.23.* are still in progress this week.
Date: 2012-01-29 21:16:09 UTC The workings will be done tonight on 91.121.*
We continue tonight and the next nights for 94.23.*
Date: 2012-01-25 09:01:09 UTC Work is still being processed on 91.121 .*.*
Date: 2012-01-22 02:05:04 UTC Worktasks continue every night from Monday to Friday.
We should finish this week the 91 121.*.* , and then move to the other networks.
Date: 2012-01-12 20:03:14 UTC We continue the workings tonight between 00:00 and 08:00 with the network 91.121.*.*