We will update the switch torque n5 pcc-26/27 from the night of Tuesday 3rd of November to Friday 4th.
We will add spare resources to unload impacted hosts during the day of Thursday.
Impacted hosts will be released before starting the maintenance in order to avoid network problems.
Once the n5 update is done we will put the hosts in production.
Update(s):
Date: 2011-11-04 14:43:12 UTC We will take the concerned hosts out of the maintenance.
Date: 2011-11-04 14:42:18 UTC pcc-27-n5 was updated and put in production.
The maintenance is finalised.
Date: 2011-11-04 14:41:47 UTC pcc-26-n5 was updated and put in production.
We will update pcc-27-n5.
Date: 2011-11-04 14:41:19 UTC The switch was liberated.
We will start the updating of pcc-26-n5.
Date: 2011-11-04 14:40:47 UTC We will start the maintenance of the hosts.
Date: 2011-11-03 12:42:56 UTC The adding of spare resources is ongoing.