FS#1780 — FS#5758 — RBX 1 : Electric switch room 0

Attached to Project— Datacenters
Maintenance
Roubaix 1
CLOSED
100%
After the additions and upgrades of the material in room 0 and consequently
the increasing of the consumed power , we must do a migration of the electrical source
on the B way of the room


3 steps :
- migration of the equipments of the room to the way B.
- modification of the way A
- return in double finish way A + B

The working will take place during all the day of 8th September 2011


Date:  Friday, 09 September 2011, 17:34PM
Reason for closing:  Done
Comment by OVH - Thursday, 08 September 2011, 15:58PM

We start the work of switching.


Comment by OVH - Friday, 09 September 2011, 01:41AM

Worktasks are slower than we expected.That's why we will perform the real switching for the machines tomorrow morining.


Comment by OVH - Friday, 09 September 2011, 17:25PM

We start the switch.


Comment by OVH - Friday, 09 September 2011, 17:30PM

We are partially in shading off and we noticed two minor improvements
that we are correcting currently.

We are going to cut entirely the way A in a few minutes.


Comment by OVH - Friday, 09 September 2011, 17:31PM

We cut entirely the way A.

We are changing the electrical source.


Comment by OVH - Friday, 09 September 2011, 17:33PM

The source of the way A was modified and the double supply is again in service.

End of the operation.