FS#1615 — FS#5599 — RBX4 : adding batteries on UPS1

Attached to Project— Datacenters
Maintenance
New
CLOSED
100%
We are adding a 4th branch of batteries on the UPS n°1 at RBX4 on Friday the 8th of July between 8h and 12h.
The UPS will be in by-pass during about 1 hour.
Date:  Monday, 11 July 2011, 23:57PM
Reason for closing:  Done