We are going to add a PNI with CHARTER at Ashburn
Here the new capacity with Charter after the upgrade
- Chicago : 4x10G
- San Jose : 2x10G
- Ashburn : 4x10G
Date: Tuesday, 24 July 2018, 11:19AMHere the new capacity with Charter after the upgrade
- Chicago : 4x10G
- San Jose : 2x10G
- Ashburn : 4x10G
Reason for closing: Done
The port is up and running.
We have'nt seen any CRC and the traffic is flowing correctly.