FS#15289 — SGP Core Network - sgp-g2-a72/sin1-sgcs2-g2-nc5

Attached to Project— Network
Maintenance
Singapore
CLOSED
100%
In order to improve the datacenter network in Singapore we are going to change our second Core router of the SGP datacenter.
This new Core router will connect the datacenter in 100G links to the OVH Backbone. sgp-g2-a72 will be replaced by sin1-sgcs2-g2-nc5.

This maintenance is scheduled on Tuesday 6th of February at 10:00pm (UTC - 06:00AM on Wednesday 7th of February in Singapore time)

> http://weathermap.ovh.net/#apac
Date:  Wednesday, 07 February 2018, 01:21AM
Reason for closing:  Done
Comment by OVH - Tuesday, 06 February 2018, 22:56PM

We are going to start the maintenance


Comment by OVH - Tuesday, 06 February 2018, 23:12PM

The device is poweroff, we're replacing it.


Comment by OVH - Wednesday, 07 February 2018, 00:03AM

The new equipment is booting


Comment by OVH - Wednesday, 07 February 2018, 00:47AM

We are checking the entire configuration and put the router back to production


Comment by OVH - Wednesday, 07 February 2018, 01:08AM

The device is in production. We are monitoring the entire infrastructure