FS#15159 — Nexus 3k bhs6
Attached to Project— Network
Planned Work | |
Beauharnois → BHS-6 | |
CLOSED | |
![]() |
Summary : We have to reload switches in the following racks to take some configuration into account
Actions : Reboot of the switches
Impact : Service will be shut during 15min per device
Start Time : 2017-11-16 08:00 (UTC)
End Time : 2017-11-16 08:30 (UTC)
Duration : 30min for all switches
List of racks concerned:
bhs6-sdtor14a-n3 : T06B04
bhs6-sdtor14b-n3 : T06B04
bhs6-sdtor24a-n3 : T06B32
bhs6-sdtor24b-n3 : T06B32
bhs6-sdtor49a-n3 : T06C39
bhs6-sdtor49b-n3 : T06C39
Date: Wednesday, 29 November 2017, 13:31PMActions : Reboot of the switches
Impact : Service will be shut during 15min per device
Start Time : 2017-11-16 08:00 (UTC)
End Time : 2017-11-16 08:30 (UTC)
Duration : 30min for all switches
List of racks concerned:
bhs6-sdtor14a-n3 : T06B04
bhs6-sdtor14b-n3 : T06B04
bhs6-sdtor24a-n3 : T06B32
bhs6-sdtor24b-n3 : T06B32
bhs6-sdtor49a-n3 : T06C39
bhs6-sdtor49b-n3 : T06C39
Reason for closing: Done
Additional comments about closing: Done.
Due to Black Friday and Cyber Monday period, the maintenance has been postponed to Wednesday, 29th, same hour.
Maintenance is starting
Maintenance has finished 10 min ago.