FS#15148 — G104A19, G104A20, G104B03, G104B14, G104B16, G105B07, G105B18
Attached to Project— Network
Modernization | |
Gravelines → GRA-1 | |
CLOSED | |
![]() |
Summary: As we are continuously improving the quality of our systems, we will be upgrading our public facing network equipment to a superior model
Actions: Replace the public network device.
Start: Monday 13 November 2017. starting at 10:00 PM (UTC +02)
Affected racks: G104A19, G104A20, G104B03, G104B14, G104B16, G105B07, G105B18
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
Date: Tuesday, 14 November 2017, 01:05AMActions: Replace the public network device.
Start: Monday 13 November 2017. starting at 10:00 PM (UTC +02)
Affected racks: G104A19, G104A20, G104B03, G104B14, G104B16, G105B07, G105B18
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
Reason for closing: Done
Additional comments about closing: done
Intervention commencée.
Intervention started.
La migration de l'équipement pour les baies G104a20, G104b14 et G104b16 est terminée.
La migration pour les baies G104a19, G104b03, G105b07 et G105b18 est annulée.
Migration for racks G104a20, G104b14 et G104b16 is completed.
Migration for racks G104a19, G104b03, G105b07 et G105b18 has been cancelled.