FS#14854 — 74B08
Attached to Project— Datacenters
Maintenance | |
Strasbourg 1 | |
CLOSED | |
![]() |
Summary : We have detected a fault on the electric part of this RACK.
Actions : Replacement of the defective part(s).
Start : Wednesday July 12th starting at 6:00 AM
Affected Rack : 74B08
Impact : Shutdown of the servers while the part is replaced
Estimated Time : 2h
Date: Wednesday, 12 July 2017, 07:39AMActions : Replacement of the defective part(s).
Start : Wednesday July 12th starting at 6:00 AM
Affected Rack : 74B08
Impact : Shutdown of the servers while the part is replaced
Estimated Time : 2h
Reason for closing: Done
intervention started
Part has been replaced. We will check last servers
All server ping