FS#14752 — 22A18

Attached to Project— Network
Maintenance
Roubaix → RBX-2
CLOSED
0%
Summary: We have detected a fault on the switch which requires replacing
Actions: Replace Switch.
Start: thursday 6 july 2017 at 6.00AM CEST
Affected racks: 22A18
Impact: Disconnection of the public network during the replacement time.
Estimated time: 30 minutes
Date:  Thursday, 06 July 2017, 08:42AM
Reason for closing:  Done
Additional comments about closing:  switch replaced
Comment by OVH - Thursday, 06 July 2017, 07:54AM

Replacement in progress