FS#14442 — 29A02 - 30A13 - 30B19 - 35A17
Attached to Project— Datacenters
Maintenance | |
Roubaix 2 | |
CLOSED | |
![]() |
Summary : We have detected a default on a part of the Cooling System of this room
Actions : Replacement of the defective parts
Start : Monday March 20th starting at 10:00 AM
Affected Rack : 29A02 - 30A13 - 30B19 - 35A17
Impact : None, a temporary part will be added while the intervention
Estimated Time : None, This task will be updated regularly
Date: Monday, 20 March 2017, 14:23PMActions : Replacement of the defective parts
Start : Monday March 20th starting at 10:00 AM
Affected Rack : 29A02 - 30A13 - 30B19 - 35A17
Impact : None, a temporary part will be added while the intervention
Estimated Time : None, This task will be updated regularly
Reason for closing: Done
Additional comments about closing: all done
29A02 already done.
We begin 30B13
30B19 done
We beginning 30A13
all done