FS#14226 — FS#21280 — Tank 73%

Attached to Project— Datacenters
Maintenance
Strasbourg 1
CLOSED
100%
Summary : We have detected an issue with the Automate who's in charge of the tank 73%
Actions : Replacement of the Automate
Starting : Wednesday November 16th starting at 10:00 AM
Impact : No impact is expected on the servers
Estimated recovery time : 4h
Date:  Wednesday, 16 November 2016, 12:57PM
Reason for closing:  Done
Comment by OVH - Wednesday, 16 November 2016, 12:57PM

Automate has been replaced. All is ok