FS#1403 — FS#5400 — RBX1 : tests of back up transformer

Attached to Project— Datacenters
Maintenance
Roubaix 1
CLOSED
100%
We will be doing many tests on the back up transformers of Roubaix 1.
The tests will continue till Wednesday morning and Thursday as well.
Date:  Friday, 27 May 2011, 14:49PM
Reason for closing:  Done
Comment by OVH - Wednesday, 04 May 2011, 08:15AM

We will start the tests.


Comment by OVH - Friday, 06 May 2011, 21:11PM

We carry on the tests this friday morning.


Comment by OVH - Friday, 06 May 2011, 21:12PM

All the tests for the spare transformer were done.

The spare is functional.