FS#1351 — FS#5352 — Electrical maintenance rooms 20 and 25

Attached to Project— Datacenters
Maintenance
Roubaix 2
CLOSED
100%
As a result to the problem that has been met on UPS 3 in Rbx2 (http://status.ovh.net/?do=details&id=1335),
we need to perform a maintenance on the rooms 20 and 25. The B track will be isolated on both
rooms. The dual alimentation of each server will keep the servers running.

We prepare the work and the operation should take place around 15h30 - 16h.





Date:  Thursday, 05 May 2011, 10:41AM
Reason for closing:  Done
Additional comments about closing:  The maintenances on room 20 and 25 are finished.
Comment by OVH - Friday, 15 April 2011, 16:26PM

We start the maintenance.


Comment by OVH - Tuesday, 03 May 2011, 15:51PM

The tasks on UPS 3 are finished.

We will benefit from these tasks in order to add an inverter on one of the channels of room
25. The channel A of the room 25 will be cut off from 13h30 till 17h.

The double power supply of each server will help maintaining the servers operational.