FS#5346 — vss-1/2/3/4
Scheduled Maintenance Report for Network & Infrastructure
Completed
In anticipation of the introduction of vss-1b/2b/3b new routers which will help us to get a redundant routing of \"first hop\", we pass the gateways of each vlan on HSRP.
No expected impact on traffic.

Update(s):

Date: 2011-04-21 15:34:20 UTC
We activate the routing on vss-2b/3b/4b.



Date: 2011-04-21 15:33:43 UTC
Following activation of routing on vss-1b, a part of the internal traffic was impacted from/to networks 94.23.0 57. Randomly, some ips were no longer reachable from other networks in intra ovh.



Date: 2011-04-21 15:31:57 UTC
We freeze updates of IPs FO on vss-1-6k.

Date: 2011-04-21 15:31:13 UTC
The vss-1b/2b/3b are connected on all vlans routed by vss-1/2/3/4. We configure routing this morning to enable them to resume the traffic in case of interruption of the primary routing. To do this, we need to temporarily freeze the configuration of IP fail-over successively on vss-1/2/3 (between 30min and 1h by router)



Date: 2011-04-19 13:26:58 UTC
We move to vss-4-6k.

Date: 2011-04-19 11:12:25 UTC
Now we intervene on vss-3-6k.

Date: 2011-04-19 10:17:51 UTC
We intervene on the vss-2-6k.

Date: 2011-04-14 12:06:27 UTC
The vlans routed by vss-1 were switched.
Posted Apr 14, 2011 - 10:37 UTC