The UPS 3 at RBX 2 is in default due to the fact that one of the power modules is out of service.
A technician is on the site, soon joined by another one in order to replace the necessary pieces.
The UPS is in by-pass mode now.
Update(s):
Date: 2011-05-03 13:36:23 UTC The new UPS is operational with the load. No cut off was realised
for the complete replacement of the UPS.
End of the tasks on UPS 3.
Date: 2011-05-03 09:03:42 UTC The UPS which is out of service was replaced with a new one.
The manufacturer is on the spot in order to realise the switch of the load
of the old UPS to the new one together with our technicians.
Date: 2011-04-26 09:57:06 UTC Since Thursday 21/04, the load was switched the temporary UPS (without any cut off).
Our electrician team proceed to the replacement of the device which is out of service.
Date: 2011-04-21 15:50:12 UTC The manufacturer wants to replace the entire UPS.
We have developed a procedure to replace the UPS completely
without interruption. Since Friday, a new UPS has been temporarily put in place
and wired to replace \"hot\" UPS 3 RBX2.
We start the construction phase:
- Should be set all / re-wiring of the UPS batteries
- Start in parallel
- Cutting off the old UPS
Date: 2011-04-15 11:59:05 UTC The manufacturer declared the module 1 of this UPS as unrepairable .
They haven't found the cause of the failure.
We will try to restart this afternoon on the module 2 alone by
offloading some of the load.
Date: 2011-04-12 19:15:26 UTC The intervention is still in progress.
The pieces of the inverter that are \"easy to replace\"
are not the cause.
The technician looks currently for a default on the
SELF of the inverter.