FS#1073 — FS#5084 — Preventive maintenance of the UPS

Attached to Project— Datacenters
Maintenance
Roubaix 1
CLOSED
100%
We will make a preventive maintenace of the UPS at Roubaix 1.
Date:  Monday, 21 February 2011, 20:28PM
Reason for closing:  Done
Comment by OVH - Wednesday, 02 February 2011, 12:01PM

We have detected a dysfunctioning on the isolating transformer
of UPS 1 at Roubaix 1 (room 2).

The manufacturer will intervene in order to follow up this problem.
The impact of this default is minor because the transformer is loading only
when the UPS is in by-pass mode.


Comment by OVH - Friday, 11 February 2011, 19:02PM

The maintenance on other units have been completed, and some parts have been changed as a precaution. These parts have
been delivered and the intervention of the manufacturer will take place by the end of this month.


Comment by OVH - Tuesday, 15 February 2011, 18:50PM

The manufacturer of the inverters will intervene again tomorrow
0216/2011 and thursday 02/17 to replace the weared pieces.


Comment by OVH - Wednesday, 16 February 2011, 09:32AM

The maintenance began.