FS#10224 — FS#14094 — POP TH2, FR, EU
Attached to Project— Network
Maintenance | |
Backbone EU | |
CLOSED | |
![]() |
We will continue with the migration to the new th2 infrastructure (http://status.ovh.net/?do=details&id=10069).
We will migrate the latest links before switching off th2-g1-a9.
We will start with the p19 <> th2 links then the th2-10/11/12-n5, bor <> th2 and lyo <> th2 uplinks.
Date: Wednesday, 22 July 2015, 21:07PMWe will migrate the latest links before switching off th2-g1-a9.
We will start with the p19 <> th2 links then the th2-10/11/12-n5, bor <> th2 and lyo <> th2 uplinks.
Reason for closing: Done
Yes!
All links have been migrated on th2-1-n7 (L2) + th2-1-A9 (L3).
So we have a capacity of 800G routing currently TH2 and the same for GSW, for a 1.6T Total => we can go up to 3.2T if necessary! :)
The ChaCha Deployment Team will be able to regain strength before tackling the next project ...