FS#10126 — FS#13998 — GRA <> LDN
Attached to Project— Network
Modernization | |
Backbone EU | |
CLOSED | |
![]() |
On National Day's eve, some are bridging. And we... are prodding!
This morning we went on the 100G link between the Gravelines datacenter and the POP in London.
We will go from 8x10G to 2x100G.
Date: Monday, 13 July 2015, 16:46PMThis morning we went on the 100G link between the Gravelines datacenter and the POP in London.
We will go from 8x10G to 2x100G.
Reason for closing: Done
The 100G are prodded. We are monitoring